SITE UPDATE |
Great progress onsite at MATTONE by CADRE. Window shrouds and awnings are installed, and the removal of scaffolding reveals the completed brickwork and facade features. Wall plastering is nearly done, and joinery is set to arrive next month onsite and commence installation. Internal waterproofing is ongoing, cladding is complete, and base coat painting is in progress. In the coming month, the focus will shift to stone installations, joinery installation, bathroom tiling, and external pot and paver installation, along with final ceiling work and the start of the timber batten facade.
YOUR NEW LOCAL POST OFFICE |
Only a 6-minute walk to your new local post office has just opened up on Swan Street, Richmond.
SITE UPDATE | CITY VIEWS
Tycorp has made significant strides on the MATTONE by CADRE project, with key milestones achieved recently. Final cladding installation and exterior painting are ongoing, alongside the application of waterproofing membranes on terrace areas. Staircases have been installed in all Townhouses, and internal wall plastering has begun. As scaffolding is dismantled, the exterior facade becomes visible. In the coming month, focus will shift to stone installations, continued plastering, joinery arrival in August, and the start of internal waterproofing and tiling, aiming to complete external facade works.
SITE UPDATE | TAKING SHAPE
There has been good progress on site! Tycorp has completed the exterior brickwork, the facade has taken shape. Window and door installation is underway, and all townhouses are commencing waterproofing. Over the next month, stairs will be installed next month, along with plastering the interior walls and cladding each townhouse.
WILD DESIGN AWARDS 2024 |
We are excited to announce that MATTONE by CADRE has been awarded Silver in the BETTER FUTURE – Environmental Sustainability category in WILD DESIGN AWARDS 2024.
SITE UPDATE |
Construction is progressing well. Brickwork installation is on track and nearing completion, with internal services already finalised. Skylights, roof hatches, and sustainable solar panels are in place, promoting natural light. Window installation is ongoing, with plaster delivery and cladding installation scheduled for next month.
THE URBAN DEVELOPER AWARDS 2024 |
We are excited to announce MATTONE by CADRE has been selected as a finalist in the @theurbandeveloper 2024 Awards for Industry Excellence in Sustainability.
RESTAURANT RECOMMENDATION | NEW QUARTER
Head down Swan Street to indulge in Modern restaurant set in an elegantly designed space where food is inspired by dishes of Vietnam.
SITE UPDATE | PROGRESS
We are excited to report significant progress at the Tycorp development this month! The structures for Townhouses 1 through 5 are now complete, and we’ve made great strides with the mechanical, electrical, and hydraulic services for these units. Additionally, the external insulation has been installed, and joinery procurement is underway.
AFL SEASON IS BACK |
Living at MATTONE puts you a tram ride away from the MCG, the perfect spot to catch the opening round of footy!
NEW CAFE HITS RICHMOND |
Your new Richmond local, just a 4 minute drive, or 9 minute walk to the latest hotspot.
Silvs on Kennedy is dedicated to serving fresh food every day, fuelled-up coffee and healthy meals. Located on Khartoum Street, this bright and breezy diner boasts a modern vibe of pink and brown tiled floors, a pink coffee machine on a polished concrete counter and tempting cabinets full of grab-and-go options.
Start your day the right way with a cup of Joe and chilli scrambled eggs on sourdough with zesty chilli butter, whipped feta and herbs.
SITE UPDATE | STRUCTURE
Townhouse 7 – Townhouse 10 structure has been completed with internal services commencing. Townhouse 1 – Townhouse 6 structure is ongoing and due to be completed by the end of February.
Window fabrication for all townhouses is underway and will progress on installation on site in the next month. Works commencing in February include roof structure, window & window shroud fabrication as well as the carpark soffit insulation is underway and will progress onsite.
AUSTRALIAN OPEN 2024 |
The annual Australian Open tournament has arrived here in Melbourne.
From your doorstep, it is only a brief walk and a 10 minute tram ride down Swan Street.
The convenience allows you to enjoy the day with family friendly fun.
SITE UPDATE | LEVELING UP
We are excited for the final push on site for 2023. The framing is progressing well with the southern side nearing completion, and are currently in the process of installing roof trusses. Merry Christmas and Happy New Year we look forward to providing an update when we are back in 2024.
BY THE YARRA |
The Yarra Trail at your back door.
MATTONE is located within moments of the Yarra Trail to provide a healthier Living & Working Lifestyle .
SITE UPDATE | TAKING SHAPE
Now that the concrete pour is complete on site at MATTONE, and precast panels are installed, framing is able to take shape on all townhouses.
SITE UPDATE | PRECAST PANELS
Now that the concrete pour is complete on site at MATTONE, Tycorp have now commenced installation of the precast panels.
SITE UPDATE | GROUND FLOOR SLAB POUR
We are thrilled to start works on site at MATTONE, Tycorp have commenced construction on site with the ground floor concrete pour well underway.
A CADRE FAVOURITE |
Only a 9 minute walk from your front doorstep.
Love your coffee? in your 20 minute community, you could enjoy a coffee or some brunch at Jethro Canteen.